We were in Aberdeen over the Christmas and New Year period, mostly for social reasons, but with the intention of opening up two more windows in one of the steading walls.
Ric & Geoff had stayed on for some time after we finished our September stint. We missed the last pour of concrete, in the east wing, and whilst they had made good progress on blockwork before we left, there had been plenty left to do. So our first visit was a chance to catch up on progress and check the state of the site.
Floor slab
We now have all our sub-floors in place. They had done as good a job of the east wing as they had on the rest. All are within a cm or so relative to each other and across each slab, apart from the garage floor which is 15cm higher and is the finished surface. We had not cut the expansion joints that the warrant requires us to do, for any continuous area over 30 square metres. Technically they are needed to provide a line of weakness in the event of contraction, to avoid random cracks across the slabs. However it had been raining whilst the slabs were laid and they were all under a cm or two of water when we arrived, so I expect there had been little scope in between for expansion/contraction. There were certainly no signs of any cracking, although the top few mm was starting to spall off in place, assisted by freeze & thaw. I expect we will cut the slots when we re-start work in April 2018.
Floor slabs
Blockwork
All our replacement walling has to have an inner course of standard concrete blocks laid on their sides i.e. 212mm wide. In the time they had available, Ric & Geoff got every opening that needed blockwork built up, mostly to lintel or sill height.
Having had misgivings about the whole issue of demolishing walling and rebuilding it, I was heartened with how well the blockwork tied in to the existing walling. For example Ric had started to sort out a particularly tricky piece of blockwork where the east wing joins the north wing on the courtyard side. We had removed a lot of granite because it was in poor condition and the adjacent door opening was a fairly shapeless 3-dimensional gap. He had cunningly tied in a column of blocks to form a neat internal corner that we can key quoin stones into, to form one edge of the door opening.
They had got two concrete structural lintels in place over the main bathroom window and had the padstones ready in several others.
They had embedded strips of stainless steel mesh into the blockwork at intervals, to tie into the new stonework. This means that when Ric is next up we can paint on the liquid DPM and get started on stonework, assuming we have our replacement sills and lintels. I am hoping that, once we can get the structural lintels on top of new granite, we can block out the wallheads ready for roof trusses separately from getting the outer, decorative granite lintels in place – if we need to. I expect that, if we want to go for getting roof trusses on by the end of the year, we will concentrate on building up the load-bearing walls at the expense of the gable-ends. Again, if we need to.
New/rebuilt walling
Wind
We had worried a little about the gales in November and the cold snap in December. The good news was that the only wind damage was to our builder’s fence panels, that were mostly horizontal, and to our electricity meter cupboard, where the door had completely blown off. The latter unsurprisingly had damaged hinges but I sort-of put it back together and leaned a solid lump of wood against it until we can do something more permanent – possibly some sort of strap that we can use to hold the door in place. As for the fence panels, we stood them up and used a couple of stout timber props tied into the panels to stop them blowing over again. I hope. We were particularly pleased that our shrub-guards netting survived the gales, having blown away twice over the least year!
All our shrub guards passed with flying colours! They survived the gales.
Drainage
It has rained quite a bit in the area over the last few months and we noted that…
- Our flooding problem in the track and driveway area is completely fixed!
- The short section of hedge on our north boundary right next to our track is still under water and we will want to run a short French drain to connect to the one Ric installed last year across the driveway.
- The east boundary that had flooded around the time we put our fencing and hedging in, was not too bad, mainly because water is no longer running off the fields the other side of the fencing.
- We will need the planned linear drain in front of our garage door, because water was coming of the track and ponding up. Not much, but it will make a big difference.
- The mystery excavation under the boundary fence between ourselves and the holiday let had filled with water to 40cm below ground level. I expect that simply reflects the water table in the winter and explains why…
- The bottom of the plot around out soakaway has some flooding, including a section of boundary hedging. We do need to look to a) do a bit of landscaping to make sure it does not pond up and b) see if we can help get surface water off site a bit quicker.
- The concrete sump that our septic tank temporarily drains into had water up to 40cm below ground level.
- A small point, but the drain cover is now in place over our concrete surface water tank, there is one less thing to fall into now. We did not get round to clearing the sludge out from the tank, I need to hire a bilge pump at some point.
So we are clearly not quite there yet, We need to do some minor drainage engineering. Given the high water table, we will be very interested in how our raised drainage mound performs as and when we get it in place.
Caravan and stove
The caravan was in good shape and did not look wind-damaged, but is starting to look green from algae. The drain cocks Ric has installed in the water supply meant the water heater was completely emptied and should be good to go next time we are in residence. The stove was installed in the caravan and Ric had had a test firing of it. The stove does look tiny, but we have high hopes for it.
It looks tiny, but is was highly recommended.
The stove pipe should be a good radiator.
The double-layer section o fpipe should preserve teh roof where it goes through!
Rodents
We have a bit of an issue with small furry mammals. They had got in to the caravan again and must have been desperately hungry. They had found the gauntlets that came with the stove, made of some sort of leather, and had consumed quite a large chunk of one of them. They had even come across a pair of ear defenders in the bothy that were not out of chewing range; They had eaten their way through much of the soft plastic – the foam soundproofing and the vinyl over the earpieces!
The bothy doors
When we built the bothy doors, two years ago, I made them a bit of a tight fit. By the time we got up this time around, the wet weather had made them expand a bit too much and we could no longer close them. I borrowed an electric plane from brother-in-law Bryan and took several mm off one door and painted the edge with preservative. It mostly sorted the problem, there is one point where it catches a little, I will see if it still a problem in the spring.
The tools for the job.
A satisfactory conclusion…
The weather
Having been up in the area off & on over 30-odd years, I got in the habit of expecting one or two falls of snow over Christmas/New Year. For whatever reason though (and yes, I do believe in man-made climate change), the last decent fall was way back in 2010.
- In 2013, when we first discovered the steading, the weather was chilly and variably windy and damp, but not cold enough to snow.
- In 2014, when we were putting up our fencing, it was well below zero, but still, dry and sunny, apart from one day of wind and sleet.
- In 2015, when we put the new doors on the bothy, it was chilly and damp.
- In 2016 when I dug out an inspection chamber do re-route some pipework, it was again chilly and damp.
- In 2017 we had the first significant fall of snow over the period, in seven years. We only got an inch or two, but it stayed for days, iced over and became quite a hazard. The combination of uneven ground, a capping of ice, melt-water and poor grip on my work boots meant that I landed on my bum several times a day and got quite adept at collapsing gracefully. Driving on the local back roads was exciting and the floor slabs became like skating rinks.
- I had left the dog’s water bowl outside and it had a good crust of ice on top. I lifted it out and observed an impressive array of ice crystals that had grown at angles down into the water.
Not much depth of snow, but it iced over and was lethal.
This layer of ice was on teh dogs drinking water bowl. These amazing ice crystals had grown down into the water!