We got the eastern end of the north wing ready for screeding whilst we worked on the east wing. We laid three loops of heating pipe for the kitchen area and one for the pantry. We did not lay pipe under the stairs or along the part of the north wall where we might put cupboard units. We put the second manifold between the kitchen and dining areas, between the fireplace and the north wall – this will be cupboard space. We pressure tested the four loops, with blanking pipes in the other 6 pairs of ports and had two of the compression fittings leak at 6 bars. We fixed this by using PTFE tape.
The rest of
the north wing has been our workshop and has been quite cluttered with large and
heavy items. We ended up clearing it out, finishing laying the insulation and
mesh, installing and pressurising the underfloor heating pipe and screeding it as
one (long) exercise, to be completed whist Ric is there.
Clearing the north wing
We cleared the small, loose stuff littering the floor easily enough and were left with the bigger items. We could not move stuff over the screed so everything had to go outside, across the courtyard and in through the big window. Each item was a challenge. The tables we carried between us. The aluminium folder we wheeled one end on our little trolley over scaffold board, The freezer housing we wheeled on the sack trolley at one end on scaffold planks. The washing machine and freezer fitted on the small trolley on scaffold boards. The woodworking machine was the challenge – we got it over the doorstep and across our pallet boardwalk on OSB laid on scaffold boards, then across the to window just on OSB. The run into the big window was too steep for us to push/pull, so we used our big orange ratchet straps wrapped around out external wall studwork and pulled it the last metre up and over the window sill. It was a miserable couple of hours, so we were more than glad to get it done.
Laying the last of the insulation
We laid the remaining full panels quite quickly and were left with a metre or so at the end and the area between the plant room and front door, which is where our pipes run. They all needed to surface in the plant room and it was quite complicated. We soldered the remaining lengths of 28mm copper pipe to the runs from the stove, ran them straight to the middle of the plant room, too a sharp left and brought them up against what will be the south wall, against the bottom of the stairs. We put a short length of 110mm brown pipe over the copper pipes to protect them from the screed. The cold water we ran over to the north wall, close to the rising main and both ends of the hot water loop next to the cold. The two pairs of feed/return pipes for the underfloor heating we pulled round to the east wall, mainly because they were a bit on the short side. They were a bit of a struggle to get anywhere near upright, so we left them at about 45 degrees. We filled in around the pipes with left-over chunks of board.
The services for the west wing we will run up the wall, through the joists to the upstairs en-suite then straight across the joists to the master bedroom en-suite. So we did not need to bury any additional pipes in the insulation, it was a case of taping all the joints and on with the next step.
Laying the mesh and heating pipe.
The mesh was easy, two sheets cover the width of the north wing with a bit of overlap and we covered the remaining floor with just over 4 sheets, including outside doorways. We cut the mesh for expansions joints in all internal doorways, at the west end of the dining area and the east end of the kitchen (to keep to the 8 linear metres/40 square metres limits).
We did the remaining
heating pipework as 6 loops. Three for the dining room area, one for the entrance
lobby and adjacent cloakroom, one for the utility room and one for the hallway between
north and west wings. These joined the four existing loops at the manifold halfway
down the north wing.
Pressure testing
was trouble-free, although filling 10 loops with air to 6 bars was a bit of a
struggle for our little 6-litre compressor.
Screeding
We split the screeding into four blocks. Timing was down to a) the availability of the hire bull float, b) us all being around all day and c) the weather being dry enough to mix screed.
Session one
was small – the section between the east wing and the kitchen area, around 8
square metres.
Session two was the kitchen area down to the fireplace, 40 square metres.
Session three was the dining room area from the fireplace down to the utility room/cloakroom, 40 square metres.
Session four
was the rest of the north wing up to the junction of the west wing.
We were nominally laying 65mm of screed, in practice the depth was often nearer 80-90mm, so we used quite a bit more screed. However, we ended up at the from door only mm out from the planned level, so we were right – it was the slab that was wonky, not our laying. We were knackered by the end and it will take a while to sink in that we can get going building the inside of the steading as soon as we get the slating finished. The inside already sounds rather more like empty rooms than a building site – a bit echoey.