Tag Archives: Landscaping

Clearing the courtyard

We hired a digger & dumper, to clear the piles of spoil in the courtyard and to get it levelled up. This did not go wonderfully to plan as we have had regular soakings over the last couple of weeks, which has really delayed us and added to the cost of the exercise. Ric repaired the giant sieve he made a couple of years ago, but has had to be quite brutal about pushing material through, so it has had maintenance every couple of days. About four-fifths of the material has been spread amongst our trees, he has raised some of the low points in the courtyard, but it is still all a bit of a quagmire.

We worked on the door steps into the courtyard, facing the concrete blocks under the granite sills with granite before we can get the doorsteps concreted into place.

Tidying loose ends

I was in Aberdeen for 8 working days near the start of July, to clear the decks before getting our floor slab laid in August/September.

Catching up with progress: Ric had got a lot done after we headed back south.

 

Complete the gable-end foundation
Ric had time on his last visit to lay the missing foundation for the north-west gable-end wall. I was to do the blockwork and associated concreting. The foundation is rather complicated. It includes:

  1. The foundation for the gable-end proper, to support the wall to one side of the future garage door. This is two leaves of blockwork, 50cm wide and some 2m long.
  2. The foundation of the adjoining wall on the single storey section, also two leaves of blockwork. This is set back 22cm relative to the gable-end and is about 1m long
  3. Tying this foundation into the Front door foundation, which is single leaf blockwork.
  4. The back of the gable-end foundation tying into the internal foundation that is to bear the structural timberwork for the floor joists, roof trusses, stairs and garage wall.

I measured up from as many reference points as possible, marked out the lines to follow and got going. As usual with working below ground level, I used a 1:4 mortar with plasticiser. I got the first two courses in place and filled the section with two leaves with 1:8 weak concrete. Next day I did the two remaining courses, thickening the mortar to get the required height. Because I am not sure of the finished ground level, I left the outer leaf at the same height as the inner one, I will raise it later if needed. I ran the gable-end blockwork along the full run of the foundation, it may need trimming back when we sort out the garage door, depending on what size opening we need. Anyway, it was then straightforward to run the front door and internal foundation blockwork to meet the new blockwork. Two days of effort in total.

Run an air pipe for our woodburner into the steading
Our woodburner will be used during the colder months to 1) heat hot water and 2) power the underfloor heating, supplemented by the air-sourced heat pump.

The warrant specifies an 18kW Boru Carraig Mor double-sided stove model (i.e. has glass-faced doors both sides). We did say in our conversation with the architect that we would be interested in a double-sided stove, located between the kitchen/family room and the lounge/dining room, so that we could heat both directly. However, double-sided boiler stoves are a rarity, probably for good technical reasons. We have struggled to find good reviews of this model, it is not particularly efficient (73%) and Boru stoves in general do not seem to be well rated. We will pass on it and find a higher-efficiency, better rated model. A plus for it is that it puts 13kW into water and 4kW into the rooms. With our levels of insulation that is probably about the right ratio. The majority of boiler stoves put less into water and more into the room, so we will still be quite restricted in our choices.

Whatever we decide on, we need to provide it with a source of air from outside. We decided to run 110mm pipe down then under the north wall, up into the hardcore under the slab and run an upright through the slab. The outside upright will need a cover of some sort to keep water and animals out.

I could not do the whole job because of a big pile of spoil on the inside of the wall. I dug down on the outside, then under the wall to as much over 50cm length as possible, so that the pipe would stick out the other side when we got the inside excavated. I cast a 200mm slab of strong concrete under the wall, put 100mm concrete block each side and five sections of 100mm x 50mm lintel across the blocks. For the last three lintels, I rammed dry-ish mortar up to the base of the wall, I will sort out the first two from the other side of the wall later. We were concerned about water getting into the pipework, so I dug a channel downhill to the main drain running conveniently close by and filled it with pea gravel.

I used slotted drainage pipe for the horizontal under the wall, to stop water accumulating in the pipework, the rest is to be brown pipe. I filled up the area around the pipe to lintel level with pea gravel, then covered with spoil. Less than a day of effort in total.

Cap the wall heads with mortar
Back around Easter time, I got one wall covered in a layer of 1:4 mortar. This is to protect the wall head from rain soaking down into the core of the wall and freeze/thaw damaging the structure. It also provides a flat surface to lay the blockwork that will raise our roof by the 40cm specified by the warrant – to give us enough headroom in both upper and lower floors. I even got some of the blockwork in place, but had to abandon work on it because of other priorities – demolishing the gable-end wall and filling the soakaway, as I recall.

On this visit, I needed to get the remaining wall heads protected with mortar, though I knew I would not have time for the blockwork, which we cannot complete anyway without all our lintels in place.

I started on the south wall of the north section (single-storey), then did the higher walls in the west, then east sections. It took seven builds of one- or two-bays of scaffolding to get the job done – much of the time taken was constructing and dismantling, relatively little was mixing and applying the mortar. The south wall was in poor-ish condition and needed some reconstruction before laying the mortar. The others were in much better condition and quicker to sort out.

I mixed a barrow of mortar at a time and used a large flexible builders bucket to get the mortar up the scaffolding. I then poured the mortar onto the wall heads and spread it using a bricklayers trowel. I got the mortar horizontal across and along the wall to within 5mm or so using a spirit level for close-up and a scaffolding plank for the overall levels, then moved on. The whole thing was quicker and easier than I expected. Two days effort in total.

Weeding
This was not planned. From a full clean out in April, our fencing, hedging, orchard and shrubby area was inundated with perennial weeds – mostly sow & common thistles, cotton (Scots) thistles, nettles, grasses, goosegrass and docks. Most were getting ready to flower, but had not done so, so I figured they could be safely composted.

I hand weeded the areas with plants we wanted to keep – all the areas with weed membrane and woodchip mulch. I made several useful observations: 1) the woodchip mulch is starting to break down and compost, meaning weeds are starting to take root above the membrane, 2) grasses creep over the edges of the weed membrane and grow roots through into the soil below, 3) many of the thistles are finding the slits in the weed membrane, pulling them up is easy and brings large amounts of horizontal tap root with them and 4) the stones we use to hold the membrane in place accumulate enough soil to allow weed seeds to germinate.

The rest of the plot I could & did strim. Our strimmer, a Stihl FS-40, is a brilliant, very capable, piece of kit which takes 2mm line. It excites our dog wonderfully. It is too light for the mature docks and cotton thistles, I used a spade to slash these off at ground level. I do need to look around for a better-designed slashing tool.

Spare time
Unusually, I finished ahead of schedule. I had a full day to do the odd jobs that had been lurking in the background. Amongst other things, I tidied the bothy and hung loads of hooks, to store shovels etc..

Tidying up

Most of our concrete pile has gone, we have hardcore. Lots of it!

George eventually contacted us to say that he had found someone who would deliver crushed concrete for £8.50 per tonne and take away our waste. He arranged a day, arrived with his digger and over the day got 10 truckloads loaded. A sort of downside was that the crushed concrete was more compact than the broken concrete, so around 19 tonnes arrived for every 15 tonnes taken away. We still have a big pile of broken concrete.

So we have plenty of hardcore – 186 tonnes of it. My rough calculation is that we have around 240 square metres of hardcore to lay, to a minimum depth of 150mm = 36 cubic metres compacted. So the uncompacted volume will be 40+, a bit less than half our pile.

Taking the remaining pile of broken concrete and the large areas of hardstanding round the north and east sides of the steading building, I expect we have converted about half our concrete to hardcore.

Ric reckons the hardcore is good for the floor slab, but a bit coarse for dumping on the track. He did talk about it with George, who said that he could use a digger to lift the existing track surface, incorporate the hardcore and get it compacted. Our track is some 450m long, the section nearest the road and shared with West Byreleask Steading is in good condition, so we would need around 375m sorting out. If it is 3m wide, that is 1125 square metres. Adding 120mm hardcore would use 140 cubic metres, just about what we would have after a second exchange for crushed concrete. George thought it would take a couple of days to sort the 100m stretch of track that is used by George Senior (our neighbouring farmer) and which is getting rather rutted.

The trucks made a mess of the concrete on the hardstanding between the concrete and the driveway. I expect this will get worse as we get concrete mixers on site for the floor slabs.

Landscaping

Disposing of the spoil that we have generated over the last two years has been a challenge. Most of it, Ric has screened. This is slow and boring, 30 tonnes or so per day, but very effective. Ric piled the separated stones/concrete ready for us to sort through. He put the topsoil to one side. Once he had leveled up the area leading to our raised drainage mound, and cleared the courtyard of rubble, he put a whole load of screened subsoil back into the courtyard and leveled that up to a safe distance below DPC level on the foundation blockwork.

In sorting the courtyard, he uncovered a run of salt-glazed clay pipes heading from the steading towards the concrete tank. There is a lateral running off part way down. It looks as though they may have connected to a similar pipe we uncovered when we dug out the door foundations last year, in which case we should find more when we scrape down the internal floor to below slab level.

He had cleared the loose material in the north leg of the steading, broke and removed the concrete and scraped & screened the cobbles just under the concrete. He ran out of time to excavate down to floor slab level.

Surface water drain just about complete: Having leveled up the courtyard , Ric jokingly said that it was larger than some building plots he has worked on. Then he dug into it to run the missing trenches up the east and west sides to the south-facing wall, ready for the downpipes that will drain the south-facing (single-storey) roof. He put junctions in, to get to the side walls, for downpipes for the east- and west-facing (2nd storey) sections of roof. He warned us that the pipes on the west side are shallow and will not bear vehicles crossing them – not likely to happen, anyway.

And that was it, apart from one missing link: Getting an extension to the north-west corner of the building for the very last downpipe. This needs to wait until we have dug up the track to divert one of our problem field drains and got the foundation for the demolished gable-end wall in place.

 

Unwelcome delays: The digger from Buchan Power Tools broke down twice, with burst hydraulic pipes. They were a bit iffy when the second one happened, but took the old one away and let us use a more-or-less brand new one – which was much better for what we wanted – lifting spoil into the dumper. I ordered materials from Ellon Timber to let Ric get on with something whilst he did not have the digger, they arrived way too late, minus a couple of essentials.

Ric just about ran out of diesel, arranged with George to fill the jerry cans and did not get them back for several days. Ric eventually cycled in to Ellon with two of our 5l cans and filled them, to let him get something done.

On the plus side, he was only rained off for a couple of hours. Generally he had sunny but cool weather.

Another unwanted drain: Just before he headed down to Cornwall, Ric dug out the foundationless area under the recently demolished gable end. He uncovered a glazed drain that runs at least 8m under the steading, probably much further down to the edge of our plot. It looks older than the steading, whilst the brick structure (that alerted Ric to a problem in the first place) was probably a more recent addition, to channel water into it when the silage pit was built. He is suggesting we could keep it as a drain, I doubt the architect would want that. Anyway, he dug out below the soft ground and laid a 200mm foundation slab with mesh. It butts up to the front door foundation but is a bit deeper. At least we know why the front door foundation flooded when we dug it out.

I still think this is where we heard running water when we first bought the property, it must still have been active. In which case, it may be the drain that the architect knew about and wanted us to divert. In which case the land drain we discovered under our foundations last year is a sort of unwelcome bonus.

What next? We had not quite got as much done on our priorities, as we would have liked. I will aim to be back up for a week in July, whilst Jill is on holiday. I will do the blockwork for the new foundation and carry on with capping the walls.

Ric suggested I phone our youngest brother Geoff, to see if he could take a working break in September, to help get the floor slab laid – he had seen Geoff at work & felt he would make a good job of it. I phoned Geoff, he thought he could combine it with a holiday, in which case Ric would do another block of work, arriving a couple of weeks early to be sure that we got all the floors scraped down and cleared. That way, the two of us could barrow whilst Geoff finished the slab. Sounds like it might all be on to get a floor slab in this year. In which case roof trusses the following year would be a distant possibility.