Category Archives: Ornamental

Tidying loose ends

I was in Aberdeen for 8 working days near the start of July, to clear the decks before getting our floor slab laid in August/September.

Catching up with progress: Ric had got a lot done after we headed back south.

 

Complete the gable-end foundation
Ric had time on his last visit to lay the missing foundation for the north-west gable-end wall. I was to do the blockwork and associated concreting. The foundation is rather complicated. It includes:

  1. The foundation for the gable-end proper, to support the wall to one side of the future garage door. This is two leaves of blockwork, 50cm wide and some 2m long.
  2. The foundation of the adjoining wall on the single storey section, also two leaves of blockwork. This is set back 22cm relative to the gable-end and is about 1m long
  3. Tying this foundation into the Front door foundation, which is single leaf blockwork.
  4. The back of the gable-end foundation tying into the internal foundation that is to bear the structural timberwork for the floor joists, roof trusses, stairs and garage wall.

I measured up from as many reference points as possible, marked out the lines to follow and got going. As usual with working below ground level, I used a 1:4 mortar with plasticiser. I got the first two courses in place and filled the section with two leaves with 1:8 weak concrete. Next day I did the two remaining courses, thickening the mortar to get the required height. Because I am not sure of the finished ground level, I left the outer leaf at the same height as the inner one, I will raise it later if needed. I ran the gable-end blockwork along the full run of the foundation, it may need trimming back when we sort out the garage door, depending on what size opening we need. Anyway, it was then straightforward to run the front door and internal foundation blockwork to meet the new blockwork. Two days of effort in total.

Run an air pipe for our woodburner into the steading
Our woodburner will be used during the colder months to 1) heat hot water and 2) power the underfloor heating, supplemented by the air-sourced heat pump.

The warrant specifies an 18kW Boru Carraig Mor double-sided stove model (i.e. has glass-faced doors both sides). We did say in our conversation with the architect that we would be interested in a double-sided stove, located between the kitchen/family room and the lounge/dining room, so that we could heat both directly. However, double-sided boiler stoves are a rarity, probably for good technical reasons. We have struggled to find good reviews of this model, it is not particularly efficient (73%) and Boru stoves in general do not seem to be well rated. We will pass on it and find a higher-efficiency, better rated model. A plus for it is that it puts 13kW into water and 4kW into the rooms. With our levels of insulation that is probably about the right ratio. The majority of boiler stoves put less into water and more into the room, so we will still be quite restricted in our choices.

Whatever we decide on, we need to provide it with a source of air from outside. We decided to run 110mm pipe down then under the north wall, up into the hardcore under the slab and run an upright through the slab. The outside upright will need a cover of some sort to keep water and animals out.

I could not do the whole job because of a big pile of spoil on the inside of the wall. I dug down on the outside, then under the wall to as much over 50cm length as possible, so that the pipe would stick out the other side when we got the inside excavated. I cast a 200mm slab of strong concrete under the wall, put 100mm concrete block each side and five sections of 100mm x 50mm lintel across the blocks. For the last three lintels, I rammed dry-ish mortar up to the base of the wall, I will sort out the first two from the other side of the wall later. We were concerned about water getting into the pipework, so I dug a channel downhill to the main drain running conveniently close by and filled it with pea gravel.

I used slotted drainage pipe for the horizontal under the wall, to stop water accumulating in the pipework, the rest is to be brown pipe. I filled up the area around the pipe to lintel level with pea gravel, then covered with spoil. Less than a day of effort in total.

Cap the wall heads with mortar
Back around Easter time, I got one wall covered in a layer of 1:4 mortar. This is to protect the wall head from rain soaking down into the core of the wall and freeze/thaw damaging the structure. It also provides a flat surface to lay the blockwork that will raise our roof by the 40cm specified by the warrant – to give us enough headroom in both upper and lower floors. I even got some of the blockwork in place, but had to abandon work on it because of other priorities – demolishing the gable-end wall and filling the soakaway, as I recall.

On this visit, I needed to get the remaining wall heads protected with mortar, though I knew I would not have time for the blockwork, which we cannot complete anyway without all our lintels in place.

I started on the south wall of the north section (single-storey), then did the higher walls in the west, then east sections. It took seven builds of one- or two-bays of scaffolding to get the job done – much of the time taken was constructing and dismantling, relatively little was mixing and applying the mortar. The south wall was in poor-ish condition and needed some reconstruction before laying the mortar. The others were in much better condition and quicker to sort out.

I mixed a barrow of mortar at a time and used a large flexible builders bucket to get the mortar up the scaffolding. I then poured the mortar onto the wall heads and spread it using a bricklayers trowel. I got the mortar horizontal across and along the wall to within 5mm or so using a spirit level for close-up and a scaffolding plank for the overall levels, then moved on. The whole thing was quicker and easier than I expected. Two days effort in total.

Weeding
This was not planned. From a full clean out in April, our fencing, hedging, orchard and shrubby area was inundated with perennial weeds – mostly sow & common thistles, cotton (Scots) thistles, nettles, grasses, goosegrass and docks. Most were getting ready to flower, but had not done so, so I figured they could be safely composted.

I hand weeded the areas with plants we wanted to keep – all the areas with weed membrane and woodchip mulch. I made several useful observations: 1) the woodchip mulch is starting to break down and compost, meaning weeds are starting to take root above the membrane, 2) grasses creep over the edges of the weed membrane and grow roots through into the soil below, 3) many of the thistles are finding the slits in the weed membrane, pulling them up is easy and brings large amounts of horizontal tap root with them and 4) the stones we use to hold the membrane in place accumulate enough soil to allow weed seeds to germinate.

The rest of the plot I could & did strim. Our strimmer, a Stihl FS-40, is a brilliant, very capable, piece of kit which takes 2mm line. It excites our dog wonderfully. It is too light for the mature docks and cotton thistles, I used a spade to slash these off at ground level. I do need to look around for a better-designed slashing tool.

Spare time
Unusually, I finished ahead of schedule. I had a full day to do the odd jobs that had been lurking in the background. Amongst other things, I tidied the bothy and hung loads of hooks, to store shovels etc..

The Festive season

Planning: We had done a little planning over the run up to Christmas. We were to be in Aberdeen for the best part of two weeks, but with little steading time.
I needed to correct the problem Building Standards pointed out with our foul drain – swapping a 90 degree bend with two 45 degree bends in our backdrop to the main bathroom inspection chamber. I bought the extra bits to take up with me.
We renewed our public liability insurance for the site.
I endeavoured to contact Stevenson & Kelly, who are based near Balmedie and manufacture roof trusses. This was not initially successful with my emails getting lost. Once I got a direct contact email address, just before Christmas, I was in.
On site:

  • We had put webbing straps over each end of the caravan, attached to large granite boulders, to stop the caravan blowing over. One strap had worked itself off. Both showed wear marks on the caravan skin where metal parts had rubbed against the metal skin of the caravan. Clearly we had had strong winds between September and Christmas. I put the missing strap back and wrapped padding around the metal parts to stop them rubbing directly.
  • I had had a roll of heavy duty windbreak netting delivered, to put along the southern boundary, which is where our strongest & most regular winds seem to come from. It was a perforated plastic mesh rather than netting, I used a pack of removable cable ties to fix it on.
  • I dug up the main bathroom inspection chamber, disconnected the backdrop and pulled the rodding point out from the chamber riser. Oddly enough, the two 45 degree bends fitted exactly where the 90 degree bend had been and I was able to slot it all back together, switching the junction that included the rodding point round 90- degrees so that it provided access down the backdrop rather than up the drain into the steading. No trimming to size needed. I did not have a spare riser, so I put the one with the rodding hole on top of the other one. We can swap it back out next year if needed. I took photos and emailed them to Building Standards. They did not reply before we left to go south, so I filled the trench up to the level of the second riser.
  • We had realised that we did not drain our water heater back in September and feared for it. Quite rightly. I put the water back on and noticed drops of water appearing underneath. I pulled the cover off but could not see where the water came from. I did track it down – a pinhole in the pipe that takes heated water out of the combustion chamber that carried a tiny jet of water over the wall of the cupboard where it ran down. I consulted with Ric and decided that there may be other leaks waiting to show themselves – we will buy a new heater.
  • Out daughter Mairi & boyfriend Ian were up and wanted to do something – I gave them breaking bars and got them to open up the missing window in the south-facing wall of our single-storey section.
  • I planted out our four bargain fruit trees bought last May – Egremont Russet apple, Worcester Pearmain apple, Bramley’s Seedling apple and Merryweather damson – in our orchard patch in the south-west corner of our plot, we had laid out the weed membrane last September. I used our roll of plastic mesh to make rabbit guards for the trees. We had to sort out the area of conifers we had planted on the north side of our plot last September. Most of the rabbit guards were leaning at angles, two had removed themselves and were on our concrete pile. It looked as though they had been wind-blasted. The conifers had suffered badly, but we patched up the guards and put extra stakes in to hold them down.
  • Right at the end we went over to see another couple who are converting a steading, the far side of Ellon. They are living in a caravan with their two children, have an L-shaped steading and 4.5 acres of field. They have a sheltered access from their caravan into a large shed/workshop. They will work with a builder to get the steading watertight, rather the way Ric is helping us out, then finish the rest themselves. It is good to know others who are in a very similar position to ourselves. They are even expected to build a raised drainage mound as well!
  •  

    More hedging and trees, also a Building Warrant

    We were back in the area for a few days at the end of May, again making best use of the bank holiday. Over the last year or two we had been bringing on an array of shrubs and trees that were destined for the steading. Come the late-May bank holiday, we decided the time was right. So we drove up in the Ford Galaxy, jammed tight with potted trees and shrubs. We also saw an interesting addition to our water supply, I expect Cadger must have been back after we left in September. We think it is to help stop it freezing up…

    Our own shrubs & trees: Being effectively container grown, they mostly had proper root balls, so our hedging technique was not suitable – we had to struggle with a spade, digging out as best we could in the usually stony ground – slow and dissatisfying.

    Our conifers mostly went into a patch on our north side (that we had covered with weed membrane on a previous visit), not far from where the caravan is at present.

    The trees we planted at 5m intervals along east and west boundaries, continuing from the ones we planted the previous November. We gave them proper tree stakes and rubber tree ties. Most needed two of the spiral tree tubes, or the solid plastic tubes that we had acquired at home and brought up with us. Several of the trees had sentimental connections. We had copper beeches from Spilsby, where I was born & brought up and Bucksburn, where Jill was brought up. We had a cherry plum that a friend of ours in Lowestoft donated and so on. We had a couple of cherry plums that Jill’s Mum, Lesley, had propagated from trees right next to Slains school. We ran out of room, so had to do another stretch of strimming and putting down weed membrane, this time a bit of a way along the southern boundary from each end.

    Caravan: We had had a message from William at Nia Roo that the truck delivering the caravan had trouble because of waterlogging where our track runs onto our property. So we were unsurprised to find the caravan put up against the north wall of the steading on the concrete hardstanding. There was quite a mess. The drop off the track was well rutted, a couple of our fence panels were fairly smashed up – I think they used the panels under the wheels of their truck to get it back on the track. Finally, quite a few of our slates were on the rutted area – they were in small pieces. Again they had probably used them to get their truck out. We also saw bits of broken plastic – a vent cover over the shower on the caravan roof was no more. We were not well pleased. We tidied up the broken slates, flattened the fence panels almost back to normality, filled in the ruts, then levelled up the caravan and checked it out.It was fine inside but obviously nothing was connected up. Still very nice to escape into during showers and for lunch breaks.