Monthly Archives: September 2017
Preparing to rebuild walls
Creating the floor slab – II
The Plan
We had booked our concrete over three consecutive mornings. I went with the volumetric mixing trucks because they have up to 6m of reach from the back of the truck and because they can hold 9+ cubic m of materials, however the trucks are 8m long, much bigger than barrel mixers, so we had to do some rearranging on site to give them access. The first day we would fill the garage and master bedroom areas in the west wing, with one load, estimated 7.6 cu m. The following day we would use two loads to fill the north wing, estimated 14 cu m. Then on the third day, do the east wing, estimated 7.6 cu m.
The Reality
We used more concrete that I expected: My estimates were bad, I had assumed a dead-level blinded surface and exactly 125mm depth of concrete. There was a few cm variation within each discrete area (master bedroom & garage in the east wing, the north wing and the east wing) and some variation between them. So the garage area base was not exactly 15cm higher than any of the other areas. These differences were significant. If the north wing, for example, was just 1cm lower than it should be relative to the other areas, we would need almost one extra cubic metre of concrete. My other mistake was to assume that the extra volume to fill the troughs (along the sides of the east & west wings, to support structural timber) were to be spread evenly across all the floor area.They were not. So I particularly underestimated the amount of concrete for the east and west wings.
Both my brothers told me, after the event, that I should have added 10% to my estimate and ordered 33 cubic metres.
Day 1
Anyway, the truck turned up on the first day. We got him to pull up in next-door’s driveway and back up to the master bedroom area. We had parted our fence, so the truck could get as close as possible: We will patch it up once the job is done. It went very smoothly. The concrete was set up for a C35 mix and was fairly runny and well-mixed, so flowed easily. By adjusting the number of chutes on the end of the mixing auger and the direction of the auger, we really did not have much raking to do. My youngest brother, Geoff, did the skilled work. He had a laser level that stood at one end of the area and a receiver that he fixed at the right height on his tamping tool. If the tool was low, it made rapid beeps, when too high, it made slow beeps. When it was at the required level it made a continuous tone. So with a minimum of fuss we got the master-bedroom area filled.
It had used at least a cubic m more that I had estimated and the driver thought he did not have enough materials to fill the garage area, so we rescheduled for a separate job over a fourth day. This was annoying, but not disastrous. Geoff used his concrete roller to push the aggregate down, then his float at intervals to smooth out the surface. It rained, but we still got a good surface.
Day 2
The following day a different driver turned up with a smaller truck. he backed up to what will be our garage door and filled the garage area. We opted for a stiffer mix, which was bit more work, but should allow a better finish, since it is the final surface (no insulation or screed on top).
Annoyingly it rained more heavily than the previous day, but again Geoff got a good smooth finish. Ric spent part of the day clearing lintels and granite out of the way so the truck could back up next day to the north wing through two openings.
Day 3
We got the first truck load in the west half of the north wing and got the full 9 cubic m. We were a bit concerned about whether we had got the area more or less that half-filled. We also had to get the concrete spread over a longer distance. Ric constructed a separate chute from a sheet of galvanised steel on a wooden frame and, when the truck reappeared an hour and a half after leaving, it worked perfectly. As it happened, we used 6 cubic m from the second load – I think the floor must have been, on average, a bit higher here.
The galvanised sheet on the chute came out looking polished and shiny – just like new. Was this the abrasive action of the flowing concrete, or a chemical thing?
At one point the driver did say he would had enough concrete on the first day to finish the garage area, after all. Hey ho!
On the final day, the driver loaded a full 10 cubic m of material on the truck, got it backed up to the bathroom window area and, with Ric’s chute, got the whole area filled with one load. Just. There was about a bucket of mix left over. It rained again and Geoff worked a smooth surface under water.
We used 33 cubic m of concrete in total – my estimate of 30 illustrated exactly why I needed to have used the ‘add 10%’ convention. Laying concrete is stressful because of what can go wrong and the difficulties with correcting mistakes. Aberdeen Concrete ltd made it much easier than it could have been. They were helpful and we only paid for the concrete we needed. But we were all relieved once the last load went in. We did have to clear quite a lot of space to allow their trucks to get backed into the opening we wanted to use.
Having spent the last three years climbing about inside the steading, it is quite strange walking on a flat, hard, continuous surface. The drain pipes look much more professionally installed now they poke vertically out of the concrete and it is blessing not to be tripping over the external electrical cables and water supply. We know from the puddles on the concrete that the surface varies by less than 1cm over each area. It will be a good base for the insulation panels and screed.
Creating the floor slab – I
We pushed on with our main priority – getting a concrete floor slab in place. A job of many layers…
First, clean up the excavation
We squared up the excavation, clearing bits by hand that the digger could not get to – this was quick, a few hours and barrow-loads for the whole floor area. I spread the trimmings across some of the low areas. We temporarily removed most of the drain pipe we had placed the year before, to make access easier and avoid damaging the pipes. We left the drain for the cloakroom area in the north wing, because it only stuck out by a metre or so, and the deep drain in the bathroom area in the west wing, because it was still (just) buried in the subsoil.
1 – Hardcore
Next up was the 200mm layer of hardcore. We started in the garage area because it was easy access and small. It would also let us access the master bedroom area beyond. Ric used the digger to load the dumper and drop the hardcore in the area we were working. I spread and levelled the hardcore, working from the back of the area towards the entrance. The hardcore is brutal stuff and was a pain to work with. It includes hefty lumps of broken concrete/stone up to 15cm long and the matrix looked like a mix of smaller broken concrete/stone and quarry dust. The big stones seemed to ‘float’ to the surface when dropped from the dumper, I spent a disproportionate amount of time and energy shovelling or throwing them by hand into the un-filled areas. I spread it by eye, trying to get it 5cm or so above the compacted level we needed. It got easier with a bit of practice, eventually I had no problem getting a decent regular surface with no more that 3-4 cm difference in height over the area. We filled the area then used the wacker plate to compact it. That worked a treat. After four runs – along, across, along and across – it compacted down the expected 50mm and had all locked solid.
We built a ramp of hardcore to get the dumper truck in and out – 6 dumper loads. We left the long sides clear of hardcore to form troughs along the edges, about 50cm wide at the top and 20cm at the bottom. These will fill with concrete, to thicken the slab as per the architects design – to support the structural timberwork that will hold our floor joists up. We did not bother in the places we had already laid foundations, these will support the slab directly. We cleared the hardcore ramp into a space we had left, compacted the whole lot and that was job done. We put the pipes back in and had to use pickaxes to break up the compacted hardcore, a couple of hours of hard labour. Lesson learnt – we will put the pipes back in place before compacting!
The following day, Ric built hardcore ramps to get access to the long north wing and the east wing. Then it was a lot more of the same – empty a dumper-load, pick out the big stones on the surface and drop them out of harms way, level with a shovel and, when the area was filled, compact it.
In the north wing we needed to complete the pipe that will feed air to our woodburner – I had run the pipe under the wall from the outside but could not finish it because there was a pile of spoil inside. Ric had uncovered the end of it when he excavated the subsoil out, it projected about 50mm into the floor space so that it will be easy to get at, to finish off. I waited until we got the run of hardcore right up to the pipework, connected a pipe to halfway across the floor and put an upright on the end of that. We dumped the next loads of hardcore right on top of the pipe, then carried on as normal.
In the east wing, we left the long edges clear of hardcore, to form the troughs for thickening the floor slab, just as we did at the west end.
After three days work, we had all 230 square metres covered in hardcore and compacted. We had used 110 of our 180 tonnes of hardcore, more that I estimated, but we are not short of the stuff. I guess we had over-dug some areas e.g. because of obstructions.
2 – Running services through the floor slab
We had already laid two armoured electrical cables, originating in the plant room area, near the future front door. They both run through the master bedroom area and into the south run of drain trenches. One is for the bothy and diverts off and (temporarily) above ground under the caravan. The second carries on all the way beyond the septic tank, where it will power the pump for our raised drainage mound. We have also laid a 20mm blue water pipe alongside the cable that runs to the bothy. It too starts its journey in the plant room, where the rising main will appear above concrete. This pipe is in use as our temporary water supply to the caravan, we will run the pipe and cable into the bothy once the caravan is finished with.
We want to lay a third electrical cable, for our polytunnel. It will run from the plant room, along the full length of the north wing and across the west wing to our family bathroom area, where it needs to exit the building on the east side through the foundation opening. We are burying all the cables and the pipe in the blinding layer, above the hardcore and below the damp proof membrane.
We did one other job at this point, testing the reinstated drains for leaks. We bunged up one end of each pipe at the inspection chamber, filled the pipe with water and left it for ages to see if the level dropped. They did not, they all passed with flying colours.
3 – Blinding
The 50mm of blinding helps level the surface and protects the damp proof membrane from being punctured by stones in the hardcore. On advice from our builders merchants, we got 20 tonnes of quarry dust delivered. This is more gritty than the sand I was expecting to use and compacts well. Plus it is half the cost. We divided the floor area up into equal-sized segments and put a dumper-load – a tonne or so – in each segment. We raked it out roughly level then used a home-made screeding rake to level it out and compact it. This was one of our short, fat, kwikstage scaffold boards on its side, with a handle attached. We even put a spirit level on it to work out when the blinding was levelled. The tool was surprisingly solid and heavy and using it was hard and slow work, but after enough runs across at different angles, it produced a very flat, compact, smooth finish. We finished off with a single run of the wacker plate for good measure. We used a couple of extra dumper loads to line the edges and bases of the troughs we had left in the east and west wings. The three electricity cables and one water pipe were duly buried. They all come up together out of the blinding, cable-tied together, in a corner of the plant room area.
4 – Expansion joint
We are required to put an isolation joint round the perimeters of all the slabs, to accommodate expansion of the slab. I used 13mm bitumen board, which is a soft fibreboard that I could cut with a Stanley knife, but which went quite floppy in the rain. I cut the boards into strips – 17cm wide (7 per board) for most of the perimeter and 40cm (3 per board) in the troughs. It was my least-favourite job to date – slow and too much bending, standing & kneeling. We ran the board into our doorways and the various nooks & crannies in our walls. The positive in all this is that the damp proof membrane will be protected from sharp edges in our walls.
5 – Damp Proof Membrane (DPM)
We used 1200 gauge (300 micron) polythene DPM in standard 4m x 25m rolls. We always worked across the floor area between outside walls, using PVC single-sided tape to seal the 400mm overlaps. We did not bother with the double-sided tape we had planned to use. The open areas were easy. Where we had a pipe coming up, we cut a slit, dropped the membrane over the pipe, then cut a small square of membrane that we cut accurately to the diameter of the pipe, slid down and securely taped to both pipe and membrane. It was a lot more tricky sorting out the various door recesses and the troughs. We had to cut and patch it a lot – a sort of giant craft activity. The tape was very effective, even on damp membrane, but was not so good when rain puddled up. I also found by experience that DPM is not the thing to do on a breezy day – at one point I had to give up and wait until the wind died away.
6 – Reinforcing mesh
The last job before we got the concrete mixers in was to lay the reinforcing mesh. We used 8mm A252 panels 3.6m x 2m on 70mm supports. This in theory gives us at least the required 25mm of cover over the mesh, even where the mesh panels overlap. We made slow and steady progress, working through a handful of 9” angle-grinder disks cutting the panels to allow for pipes and recesses. Moving the panels into place was definitely a two-person job, it was too easy to catch the membrane and make holes in it. We overlapped the panels by 30cm and wired them together – using a twizzler device to wind the wires and tighten them. It was all solid enough to walk on. The most awkward bit was where one of our pipes gradually sloped up above the blinding and up to mesh height. I cut out a couple of small panels of mesh and used a sledge hammer to form them into curved up-stands that went over the pipe and were tied to the mesh either side. Hopefully there will be enough depth of concrete that they will be covered!
Excavating our floor
We headed up to Aberdeen, for our last block of work for 2017, with a cunning plan: To drive half-way the night before, stop overnight and get to the steading early enough next day that we could get something useful done as soon as we arrived. We had booked in at the Chester-le-Street Travelodge, expecting to get there around 10.30pm.